project Details
Title | Description |
---|---|
Project Name | Construction of Pre-Fab Factory Building with 2 storied Office Building on 8000㎡ MEPZ Plot |
Project Detail | Soil Test Architectural Design Construction Consultacy |
Project Area | Land Area: 8000㎡ Factory Building:4000㎡ Office Building:2000㎡ With Guard Room, Generator Room and Other facilities. |
Client | Kotobuki Industrial Co. Ltd, Japan Kotobuki Bangladesh Ltd. |
Construction Lead Time | 8 Months |
Project Time Line
Project Title | Project Description |
---|---|
January 2011 | Kotobuki Industrial Co., Ltd. (J-KOT) participated Bangladesh Industrial Tour, organized by Pleiades. |
March 2011 | J-KOT participated EPZ tour by Pleiades, then J-KOT decided to invest at Mongla EPZ (MEPZ)Pleiades offered Incorporation & BEPZA contract work. |
November 2011 | Kotobuki Bangladesh Ltd. (B-KOT) has established |
February 2012 | Agreement between B-KOT and BEPZA has donePleiades offered consulting for Factory |
March 2012 | Soil test at B-KOT's Plot at MEPZ |
April 2012 | B-KOT issue work order to PCCL for consulting(several times drawing revising) |
September 2012 | Drawing was approved by MEPZPCCL offered Construction for Factory |
November 2012 | B-KOT issued work order to PCCL for construction |
December 2012 | Start Construction |